Client: Jones Hargreaves Duration: 8 weeks Location: Rainham, Kent

Working on behalf of Commercial Building Consultants Jones Hargreaves, 7formation were to undertake the full dilapidation works on a 2000 sq ft. office / warehouse unit.

The roof received a chemical clean along with cut edge corrosion treatment and a new epoxy coating, gutters were cleaned and lined. A new roller shutter door was installed as access to the warehouse, along with external block paving repairs.

Internally the warehouse floor received a diamond grind preparation and 3 coats of high gloss epoxy paint. The offices, kitchen and toilets also received a full makeover with new ceilings, floor coverings and decoration throughout. The warehouse and offices were re-wired with the introduction of LED lighting. This project was completed in 4 weeks resulting in the unit only being unoccupied for an 8 weeks period.