Project Description

Client: COOP
Location: Carlton
Duration: 32 weeks

7formation has just begun work on our first project for Co-Op-a 450 square meter new build supermarket in Carlton, North Yorkshire. Starting in November 2022 this will be a 32-week project, delivered to the client in the summer of 2023. Upon completion of the clearances, the first phase substructure consists of drainage, car park formation, and laying of foundations.

7 Formation will begin phase 2 of the superstructure by constructing of the steel frame, which will eventually support the brick and block work as well as cladding and roofing panels. Complemented with an Anglian marly roof coving.

The final phase will include the external works to the store including tarmac, block paving, and landscaping with internal fitout by others.