Over a 9 week project, 7formation were tasked with a complete refurbishment for Next at their store in Coventry.
This was our first project for the British clothing retailer. As the principal contractor on this job we gave the store a complete make-over, including a new cashier area, racking, flooring, ceiling and fresh wall décor.
One notable change to their store was the redesign of the fitting room area, which has given the area a much more spacious feel. This element of the work is the area in which we added the most value as we helped to influence the design to give the best feel for the customer. Our clever phasing of the project also allowed for some of the store to remain trading, which added value to the client by minimising loss of income in the project.
Key Facts
Value
£400,000
Client
Next
Location
Coventry
Duration
9 Weeks
Sector
Retail



Project Team


Tom Andrews
Contracts Director

Ben Gooch
Project Manager

Owen Sheppard
Commercial Manager