Jewson – Woolwich

Project Description

Client: Jewson
Location: Woolwich
Duration: 28 weeks

7formation were tasked with delivering Jewson’s first Jewson-Go outlet at Woolwich. Acting as principal contractor, the works
involved the fit-out of the new format of a click and collect outlet, and the construction of a concrete vehicle ramp to access parking and storage levels.

Selco Kingston

Project Description

Client: Selco
Location: Kingston
Duration: 14 weeks

7formation were tasked with the full refurbishment of the Selco branch at Kingston. Works included the strip out, installation of mezzanine, complete M&E services. Creation of new offices and retail area, including the provision of a staff amenity area. External works included concrete hard standing, tarmac finishes and perimeter fencing along with car park lighting

Testimonial

”Steve, I just wanted to drop you a quick line regarding the work recently completed at Selco Kingston. You will no doubt appreciate my general reluctance to introduce a new Contractor to the Selco fit-out team but I have to say that Kym has been absolutely exceptional in the way he has tackled this project. A great set of well-managed sub-contractors with a very high standard of finish. Kym has proved himself to be reliable, respectful and dedicated in his conduct and I am genuinely looking forward to working with Kym and his wider team. It is not every day I send an email like this so keep up the good work! Regards. R.Chandler – Head of Construction

Jewson Royston

Project Description

Client: Jewson / Saint-Gobain
Location: Royston
Duration: 12 weeks

Acting as principle contractor, 7formatio were tasked with carrying out full refurbishment works at Jewson’s Royston store. Whilst the store remained fully operational, careful planning and phasing of the project ensured that the impact on the clients, staff and customers were kept to a minimum.’

Saint Gobain – Pritex

Project Description

Client: PRITEX / Saint-Gobain
Location: Wellington Somerset
Duration: 26

Acting as principal contractor, 7formation were tasked with the internal refurbishment of the PRITEX Factory Building, in conjunction with the reconfiguration to the existing parking area’s and the approach roads serving the factory located at Wellington – Somerset. External works included the forming of a new entrance and the installation of automatic gates and barriers. An extensive re-work of the roads and car park areas to a lorry grade finish, including surface water drainage, perimeter fencing, traffic management, and a new led lighting scheme and car charging facility. The internal works required careful planning with the works phased to allow the factory to remain fully functional. These works included the installation of a mezzanine, the forming and the fit-out of a new laboratory test area, office, canteen, and storage, along with a new engineering area and welding bay. The project was completed on programme and within budget.

SIG Valor Park

Project Description

Client: SIG Plc
Location: Slough, Valor Park
Duration: 20 weeks

Acting as Principal Contractor 7formation were tasked with converting an existing warehouse and office building to suit the specific operational requirements of SIG. The works were completed over a 20-week programme.  Externally works included the mass filling or a 12,500sq ft rampway serving the dock levelers and re-casting 200mm thick reinforced slab to form the new concrete apron.15 dock levelers were removed, works included importing leveling and compacting approx. 2000 tons of filling
material and placing 1100 tons of concrete. 400m2 of cladding was de-skinned to allow structural steel alterations, to close existing apertures, and introduce 8no roller shutters. The warehouse floor is approx. 75,000sq ft. Within this space 1km of 12m high racking was installed along with a 2000m2 steel framed mezzanine. The warehouse was fully serviced with Wi-Fi, CCTV,
Fire alarm system, along with motion sensor lighting. Office Areas. The existing offices were refurbished to suit the requirements of the incoming personnel. This included Suspended ceilings, flooring, air conditioning, a canteen complete with appliances and furniture, a fully completed data system, comms room, CCTV, meeting rooms, transport and sales counters and racking. The 70-workstation office fit-out also included, the refurbishment of the toilet areas, ceramic tiles to floors and walls, the provision of faith and first aid rooms.’

Time-Lapse Video